A.Applied to CPC Miss - March 29th, 2005.
B.CPC´s sposorship Approval - April 19th 2005.
C.CHC Delhi started processing - May 04, 2005.
D.CHC sent passport request - May 19th, 2005.
E.Passport couriered to CHC Delhi - May 25th, 2005.
F.E-Client Changed to ´Decision Made´ - June 6th, 2005.
G.Passport received in a brown envelope along
with all the documents (thru registered post)- June 9th, 2005.
H.Visa issue date on the passport - June 2nd, 2005.
So the total time taken is 2 months and 12 days. I did few mistakes intially when submitting the forms however I corrected it and proactively sent it in.
Hope this information helps.
Thank you all for your support and goodbye.
Arnab M
[09-06-2005,17:28] [**.158.101.30] arnab |
|
(in reply to: TimeLine CHC Delhi - Spousal Visa) U are so lucky!!!!!!
Good luck to you both.
Mine application is 5 months inside and counting..
Haven´t heard anything back from them yet, since the very first letter.
[09-06-2005,17:48] [***.123.170.131] SW |
(in reply to: TimeLine CHC Delhi - Spousal Visa) Congartulation Arnab...Of course your wife is the luckiest one. New Delhi is the fastest in the world. I am here in Canada and waiting for six months as they Transfered my file to Local CIC. Now I relized that I must apply in new delhi instead of in Canada class.
we welcome your wife in Canada as a new PR.
Good Luck & Cheers.
[09-06-2005,17:52] [**.194.254.96] N.K. |
(in reply to: TimeLine CHC Delhi - Spousal Visa) Oye Arnab...
Congrats man... Now its Party Time...
When are we invited for Dinner ;)
Cheerios...
- Harshal -
[09-06-2005,18:51] [**.197.173.144] - HS - |
|